Every closed cryogenic receptacle shall be provided with at least one pressure-relief device. The
pressure-relief device shall be of the type that will resist dynamic forces including surge.

Closed cryogenic receptacles may, in addition, have a frangible disc in parallel with the spring loaded
device(s) in order to meet the requirements of 6.2.1.3.6.5.

Connections to pressure-relief devices shall be of sufficient size to enable the required discharge to
pass unrestricted to the pressure-relief device.

All pressure-relief device inlets shall under maximum filling conditions be situated in the vapour
space of the closed cryogenic receptacle and the devices shall be so arranged as to ensure that the
escaping vapour is discharged unrestrictedly.

Capacity and setting of pressure-relief devices

NOTE: In relation to pressure-relief devices of closed cryogenic receptacles, maximum allowable
working pressure (MAWP) means the maximum effective gauge pressure permissible at the top of a
loaded closed cryogenic receptacle in its operating position including the highest effective pressure
during filling and discharge.

The pressure-relief device shall open automatically at a pressure not less than the MAWP and be fully
open at a pressure equal to 110% of the MAWP. It shall, after discharge, close at a pressure not lower
than 10% below the pressure at which discharge starts and shall remain closed at all lower pressures.

Frangible discs shall be set to rupture at a nominal pressure which is the lower of either the test
pressure or 150% of the MAWP.

In the case of the loss of vacuum in a vacuum-insulated closed cryogenic receptacle the combined
capacity of all pressure-relief devices installed shall be sufficient so that the pressure (including
accumulation) inside the closed cryogenic receptacle does not exceed 120% of the MAWP.

The required capacity of the pressure-relief devices shall be calculated in accordance with an
established technical code recognized by the competent authority1.

Approval of pressure receptacles

The conformity of pressure receptacles shall be assessed at time of manufacture as required by the
competent authority. Pressure receptacles shall be inspected, tested and approved by an inspection
body. The technical documentation shall include full specifications on design and construction, and
full documentation on the manufacturing and testing.

Quality assurance systems shall conform to the requirements of the competent authority.
 
1 See for example CGA Publications S-1.2-2003 "Pressure Relief Device Standards-Part 2-Cargo and Portable
Tanks for Compressed Gases" and S-1.1-2003 "Pressure Relief Device Standards-Part 1-Cylinders for Compressed
Gases".

Initial inspection and test

 
New pressure receptacles, other than closed cryogenic receptacles and metal hydride storage 
systems,
shall be subjected to testing and inspection during and after manufacture in accordance with the 
applicable design standards including the following:
 
On an adequate sample of pressure receptacles:
 
(a)         Testing of the mechanical characteristics of the material of construction;
 
(b)         Verification of the minimum wall thickness;
 
(c)         Verification of the homogeneity of the material for each manufacturing batch;
 
(d)         Inspection of the external and internal conditions of the pressure receptacles;
 
(e)         Inspection of the neck threads;
 
(f)      Verification of the conformance with the design standard; For all pressure receptacles:
(g)      A hydraulic pressure test. Pressure receptacles shall meet the acceptance criteria 
specified in   the design and construction technical standard or technical code;
 
NOTE: With the agreement of the competent authority, the  hydraulic  pressure  test  may  be  
replaced by a test using a gas, where such an operation does not entail any danger.
 
(h)      Inspection and assessment of manufacturing defects and either repairing them or rendering  
   the pressure receptacles unserviceable. In the case of welded pressure receptacles, particular 
attention shall be paid to the quality of the welds;
 
(i)          An inspection of the marks on the pressure receptacles;
 
(j) In addition, pressure receptacles intended  for  the  carriage  of  UN No.  1001  acetylene,  
dissolved, and UN No. 3374 acetylene, solvent free, shall be inspected to ensure proper 
installation and condition of the porous material and, if applicable, the quantity of solvent.
 

 
On an adequate sample of closed cryogenic receptacles, the inspections and tests specified in 
6.2.1.5.1
(a), (b), (d) and (f) shall be performed. In addition, welds shall be inspected by  radiographic, 
ultrasonic or another suitable non-destructive test method on a sample of closed cryogenic 
receptacles according to the applicable design and construction standard. This weld inspection does 
not apply to the jacket.
 
Additionally, all closed cryogenic receptacles shall undergo the initial inspections and tests 
specified in 6.2.1.5.1 (g), (h) and (i), as well as a leakproofness test and a test of the 
satisfactory operation of the
service equipment after assembly.
 